Component project methodology

It is common for internal business units to contribute to departmental projects by developing a component of the overall project. The component project process flow diagram  has been developed to provide guidance for components that relate to the generic methodology used by the overall project.

Step by step guidance, flowcharts (at activity and task level) and templates have been developed together with a set of touch points diagrams. These show the interfaces between the overall project and the component project as they move through the four project phases.

The component methodology is divided into four phases, similar to the generic methodology. Each phase has a number of project management and work management activities. Listed below are the phases and activities. For more detailed information select the title link. 

Component methodologyProject managementWork management
Concept phase PC1 Component project start up WC1 Develop component options
PC2 Component options analysis WC2 Develop preferred option
PC3 Component offer  
Development phase PC4 Component administration WC3 Options analysis (how)
PC5 Component management plan WC4 Requirements definition
  WC5 Detailed design
Implementation phase PC6 Manage component plan WC6 Produce outputs
  WC7 Test
Finalisation phase PC7 Handover  
PC8 Evaluate performance  
PC9 Close-out  

Last updated
12 January 2010