P10.1 Evaluate against success criteria
Guidance
Project success criteria specified in the business case should
be reviewed. This task reviews the project's actual performance
against those measures to determine project success. Performance
should be reviewed against both initial and final baselines. Any
variance between the initial versions and final versions of the
schedule, plan and contract need to be identified and justified.
The review seeks to identify changes to organisational processes
and procedures that should be fed back into the strategic, business
and project planning processes to improve organisational
performance.
This task also includes, in effect, an audit to ensure all
activities to finalise the project have been completed. Final costs
are determined and compared with the various estimates produced
throughout the project lifecycle to determine how well the
estimation performed.
Responsibility
The project manager has responsibility for this task.
References
Handover report
Project plan
Contract documentation
Proposal business case