Project history

Key dates

  • 18 May 2017: First sod turned to mark the start of major construction for the Bruce Highway upgrade. 
  • 16 September 2016: Fulton Hogan Seymour Whyte Joint Venture awarded the detailed design and construction contract.
  • 21 March 2016: Transport and Main Roads received tenders from Fulton Hogan Seymour Whyte Joint Venture and The Infrastructure Group.
  • 4 November 2015: Transport and Main Roads announced the shortlisted tenderers for the double Early Contractor Involvement (dECI) process. Fulton Hogan Seymour Whyte Joint Venture and The Infrastructure Group were shortlisted to submit proposals for the detailed design and construction of the Bruce Highway Upgrade—Caloundra Road to Sunshine Motorway.
  • 3 September 2015: Transport and Main Roads held a specific project industry briefing where the Expression of Interest for the double Early Contractor Involvement process commenced.

Project timeline

Late 2010 Started planning study Complete
Late 2011 Publicly released draft plan Complete
Early 2013 Publicly released preferred planning layout Complete
2013-2014 Constructed interim safety project between Martin Road and Sippy Creek Road Complete
July 2015 Publicly released revised preferred planning layout Complete
November 2015 Started double Early Contractor Involvement (dECI) tender process for detailed design and construction Complete
Late March 2016 dECI tenders closed Complete
April-August 2016 Reviewed tenders Complete
September 2016 Awarded detailed design and construction contract to Fulton Hogan Seymour Whyte Joint Venture Complete
September 2016 Start detailed design Ongoing
November 2016  Start preliminary construction
Complete 
May 2017 Start of major construction Ongoing
Late 2020 Finish construction