Burnett River Bridge replacement (Monto-Mount Perry Road)

Overview:

Reconstruction works to replace the Burnett River Bridge on Monto-Mount Perry Road are now complete and the bridge is open for use.

Location:

North Burnett.

Benefits:

The previous single-lane, timber bridge was washed away during Severe Tropical Cyclone Marcia in 2015. The new concrete bridge provides greater flood immunity and improved safety.

Regions:
Wide Bay Burnett Region, North Coast Region

Project info

Construction of the new 2-lane concrete bridge started in August 2016 and included re-aligning the road approaches to meet current design standards.

The new bridge has been built wider to accommodate 2 lanes of traffic with road shoulders for improved safety. The curves of the bridge approaches have been reduced to improve motorist visibility and flood immunity has been improved.

There will be some ongoing works until the end of June 2017 (weather permitting) to remove the temporary river crossing and restore the river banks to their previous condition. This work is not expected to impact traffic using the new bridge.

The department thanks motorists and road users for their patience while these vital reconstruction works were being completed.

Project milestones

  • Project complete - 18 May 2017 2017.

Contact details

Email: Bundaberg.office@tmr.qld.gov.au
Phone: 1300 728 390
Post: Locked Bag 486
Bundaberg Qld 4670

Media gallery

Burnett River Bridge (Monto-Mount Perry Road) information flyer

destruction of previous bridge
Destruction of previous bridge

drilling for pile installation
Drilling for pile installation

deck installation
Deck installation

bridge deck complete
Bridge deck complete

Burnett River bridge complete
Burnett River Bridge complete

Piling works and bridge approaches: September 2016
Piling works and bridge approaches: September 2016

Piling and pile cap installation: December 2016
Piling and pile cap installation: December 2016

Last updated
23 May 2017