Mains Kessels intersection upgrade Project
-
Overview:
-
This project will provide a short underpass beneath Mains Road for Kessels Road traffic with improved turn and intersection lanes and new provisions for buses, pedestrians and cyclists.
This intersection is one of Queensland’s busiest with an average of over 90,000 vehicle movements per day. Separating Kessels Road traffic from Mains Road traffic will improve safety and travel times and provide a more efficient and reliable intersection with capacity to accommodate future traffic growth.
-
Location:
-
The intersection of Mains Road and Kessels Road in Macgregor, Brisbane.
-
Completion:
-
Early works including demolition of buildings, construction of retaining walls and noise barriers, and establishment of a site office and visitor experience centre are all scheduled for late 2011.
Plans for the main construction work are on track to start in early 2012 with project completion due by late 2014, weather permitting.
-
Benefits:
-
- improved travel times and traffic flow by separating Kessels Road traffic from Mains Road
- reduced delays and congestion
- improved safety, reliability and fewer breakdowns
- reduced vehicle operating costs
- extended life of the intersection to cater for traffic growth
- improved provision for cyclists (on-road and off-road)
- improved amenity for the local community though enhanced urban design
- reduced fuel consumption, local exhaust emissions and noise levels around the intersection
-
Supplier:
-
The Department of Transport and Main Roads (Queensland Government) is delivering the upgrade on behalf of the Australian Government.
-
Funding:
-
A$300 million (Australian Government funded – Nation Building Program)
-
Regions:
- Metropolitan Region
Project info
Community engagement and preconstruction activities are continuing in 2011. Main construction of the upgrade is scheduled to start in early 2012.
Design and construction tender process
Baulderstone Queensland supported by designers Parsons Brinckerhoff have been selected as the successful contractor to design and construct the upgrade.
This contract was awarded under an early contractor involvement process (ECI). Two companies were shortlisted to compete for the contract by providing detailed planning for design and construction, ensuring thorough review of options to improve outcomes for delivery of this intersection upgrade.
Key milestones
| Activity | Timing | Status |
| Community, public engagement and displays |
Ongoing |
Ongoing |
| Consultation with adjacent property owners and businesses |
Ongoing |
Ongoing |
| Consultation with directly impacted businesses and residents |
Ongoing |
Ongoing |
| The project team gathers community comments and feedback about the intersection and starts environmental, traffic and engineering studies. |
Early 2006 |
Completed |
| Options to improve the intersection are developed and presented to the community for comments and feedback. |
Late 2006 |
Completed |
| Options are assessed using the results of community feedback, along with engineering, traffic and environmental studies. |
Mid-late 2007 |
Completed |
| The recommended option is presented to the community and submitted to the Australian and Queensland Governments for approval to move to the business case phase. |
Early 2008 |
Completed |
| The study team undertakes detailed engineering work and prepares a preliminary design and business case for assessment by the Australian Government. |
Dec 2009 |
Completed |
| The Australian Government makes a decision about funding for the upgrade. |
Early 2010 |
Completed |
| Geotechnical investigations and service location works commence. |
Mid 2010 |
Completed |
| Request for Proposals: Early Contractor Involvement process begins |
October 2010 |
Completed |
| Short-listing of two contractors to prepare bids for construction and final design |
Early 2011 |
Completed |
| Construction begins to signalise Mains Road and Omeo Street intersection to improve safety |
Mid 2011 |
Completed |
| Construction completed to signalise Mains Road and Omeo intersection to improve safety |
Mid 2011 |
Completed |
| Project land requirements finalised for road corridor |
Mid 2011 |
Completed |
| Project displays conducted in local shopping centres and precincts |
Mid 2011 |
Completed |
| Design and construct contract is awarded to winning tenderer |
October 2011 |
Completed |
| Contractor establishes site and starts pre-construction activities |
Late 2011 – early 2012 |
Pending |
| Contractor due to start main construction phase |
Early 2012 |
Pending |
| Construction completion |
Mid 2014 |
Pending |
Project Factsheets
Further information
Contact details
| Email: |
mainskessels@tmr.qld.gov.au |
| Phone: |
1800 227 804 (freecall within Australia, higher rates apply from mobiles and pay phones) |
| Post: |
Mains Road and Kessels Road Intersection Upgrade GPO Box 2439 Brisbane QLD 4004 (no stamp required) |
| Operation: |
9 am – 5 pm (GST +10) weekdays |
| SMS: |
Register at www.mkusms.com.au and follow the prompts for this free service |
|---|
Mains Kessels intersection upgrade Project: SMS registration flyer (PDF, 649 KB)
Latest news
-
Construction Activities: 13 May 2012 (PDF, 257 KB)
-
Construction Activities: 29 April 2012 (PDF, 259 KB)
-
Construction Activities: 22 April 2012 (PDF, 810 KB)
-
Construction Activities: 8 April and 15 April 2012 (PDF, 817 KB)
-
Construction Activities: 1 April and 8 April 2012 (PDF, 289 KB)
-
Construction Activities: 25 March 2012 (PDF, 282 KB)
-
Construction Activities: 18 March 2012 (PDF, 340 KB)
-
Construction Activities: 11 March 2012 (PDF, 328 KB)
-
Construction Activities: 5 March 2012 (PDF, 730 KB)
-
MacGregor Park 'n' Ride - temporary access change (PDF, 365 KB)
-
Contruction Activities: 27 February 2012 (PDF, 141 KB)
-
Temporary bus stop relocations from Tuesday 21 February 2012 (PDF, 161 KB)
-
Construction Activities: 20 February 2012 (PDF, 410 KB)
-
Construction Activities: 13 February 2012 (PDF, 360 KB)
-
Construction Activities: 6 February 2012 (PDF, 266 KB)
-
Construction Activities: Benaud Street February 2012 (PDF, 1.39 MB)
-
Construction Activities: 30 January 2012 (PDF, 343 KB)
-
Night works for week starting 23 January 2012 (PDF, 100 KB)
-
Mains Kessels intersection upgrade: project update (Summer 2011) (PDF, 2.76 MB)
-
Mains Kessels intersection upgrade: project update (July 2011) (PDF, 0.96 MB)
-
Mains Kessels intersection upgrade: project update (July 2010) (PDF, 695 KB)
-
Mains Kessels intersection upgrade: newsletter (July 2010) (PDF, 1.3 MB)
-
Geotech advertisement (PDF, 282 KB)
-
Mains Kessels interestion upgrade: Kessels Road (west) to Estoril Street (May 2011) (PDF, 1.2 MB)
Recent media statements
Last reviewed: 05 March 2012