Reconstructing Mackay/Whitsunday

Overview:

The Department of Transport and Main Roads is working to reconstruct more than 300km of disaster-damaged roads in Mackay/Whitsunday region over the next few years, following cyclone and rain events of 2010 and 2011.

The work is part of Operation Queenslander, the largest reconstruction effort in Queensland’s history – rebuilding communities, fixing infrastructure and restoring regional economies.

Location:

The works are being delivered on a number of state-controlled highways and roads across the Mackay/Whitsunday region. The works have been packaged as follows:

  • North Package
  • Peak Downs Highway Package
  • West Package
  • Bruce Highway Package
  • RoadTek Mackay
  • RoadTek Townsville
  • Other roads
Completion:

Mid 2014

Benefits:
Queensland’s road network received more damage than any other state government asset during the flood and cyclone events of 2010/2011. Reconstruction works will make the Mackay/Whitsunday region’s roads safer, stronger and better able to cope with future weather events.

The program will generate more than 1050 local jobs.
Supplier:

RoadTek, local governments and private contractors will undertake these works on behalf of the department.

Funding:

The works are being delivered under Natural Disaster Relief and Recovery Arrangements (NDRRA), a joint federal and state initiative. Under these arrangements, the Australian Government provides 75% of the funding, with 25% from the Queensland Government.

Regions:
Mackay Whitsunday Region

Project info

During the 2010/2011 summer flooding and cyclone events almost half the Mackay/Whitsunday 2600km state-controlled road network was damaged.

Reconstruction works will be progressively delivered across the region as packages of work and will include a range of works including stabilisation, shoulder widening, pavement replacement and bitumen resurfacing.

Key milestones

  • June 2011: Construction works started on the North Package 
  • April 2012: Construction works started on the West Package
  • April 2012: Construction works started on the Peak Downs Highway Package
  • June 2012: Construction works started on the Bruce Highway Package
  • October 2012: Completion of the North Package

Package information

For further information about reconstruction works in your area, please click on the links below:

Useful Links

Contact details

Email: reconstruct_mackay@tmr.qld.gov.au
Phone: 1300 736 754* (During business hours)
Fax: +61 7 4951 8555
Post:

Department of Transport and Main Roads
PO Box 62
Mackay Qld 4740

* Cost of a local call. Higher call charges apply from mobile phones or payphones.

Traffic info

There will be traffic disruptions across the network. The department will use traffic signals, traffic controllers, single lane closures and speed restrictions as required.

The safety of road users and road workers is the number one priority when delivering these works.

Your patience and cooperation is appreciated while these important works are underway.

Please slow down – roadwork safety is your responsibility too.