Cleveland-Redland Bay Road upgrade

The department is undertaking a $110 million package of works to upgrade Cleveland-Redland Bay Road.

Works include:

  • works along key sections of Cleveland-Redland Bay Road (completed)
  • the upgraded Anita Street intersection (completed)
  • duplicating Cleveland-Redland Bay Road from Anita Street to Magnolia Parade (works underway)
  • safety improvements at various intersections, including Serpentine Creek Road (completed)
  • duplicating Cleveland-Redland Bay Road from Anita Street to Giles Road (detailed design).

Benefits

  • Improves safety
  • Increases capacity
  • Improves network efficiency
  • Increases traffic flow
  • Reduces peak hour congestion
  • Reduces interchange queuing
  • Reduces travel time
  • Better road access

Key features

  • Increasing the capacity on Cleveland-Redland Bay Road through the Anita Street intersection to Magnolia Parade from 2 to 4 lanes.
  • Installing traffic lights and a pedestrian crossing across Cleveland-Redland Bay Road and Anita Street.
  • Active transport improvements.
  • Improved bus stops.
  • Safety improvements at key intersections.
  • Increasing the capacity on Cleveland-Redland Bay Road from Anita Street to Giles Road from 2 to 4 lanes (detailed design).

Funding

Investment ID 1244428 Cleveland-Redland Bay Road, Anita Street to Magnolia Parade, duplicate to 4 lanes ($97 million). Investment ID 1510961

Cleveland-Redland Bay Road, various locations, improve intersections ($12.14 million). Investment ID 1133303

Cleveland-Redland Bay Road, South Street to Boundary Road planning ($600,000).

Total investment
$110 million
Queensland Government
$110 million

Current status

Anita Street intersection upgrade

Construction started in August 2020, with the traffic signals operational in July 2021.

Cleveland-Redland Bay Road duplication (Anita Street to Magnolia Parade)

Construction is underway to duplicate Cleveland-Redland Bay Road between Anita Street in Redland Bay and Magnolia Parade in Victoria Point.

Show/hide description ( #video1 )

The upgrade will reduce congestion, improve traffic flow, and increase safety for all road users. New on and off-road active transport infrastructure will also improve connectivity for pedestrians and people riding bikes.

Safety improvement works

Safety upgrades to improve traffic flow, reduce congestion and increase safety at various intersections including Serpentine Creek Road. The upgrades started in early 2022 and were operational in March 2023.

Cleveland-Redland Bay Road future planning

A planning study to identify suitable upgrade solutions for the Boundary Road roundabout and Cleveland-Redland Bay Road (Anita Street to Giles Road) corridor started in October 2021.

Cleveland-Redland Bay Road upgrade project overviewProject map showing works at 6 sites

Cleveland-Redland Bay Road and Beach Street upgrade project map

Cleveland Redland Bay Road and Beach Street upgrade project map outlining work to be undertaken

Cleveland-Redland Bay Road near South Street upgrade project map

Cleveland Redland Bay Road near South Street upgrade project map outlining work to be undertaken

Cleveland-Redland Bay Road and Melanie Street upgrade project map

Cleveland Redland Bay Road and Mealnie Street upgrade project map outlining work to be undertaken

Cleveland-Redland Bay Road near Lakeside Boulevard upgrade project map

Cleveland Redland Bay Road near Lakeside Boulevard upgrade project map outlining work to be undertaken

Cleveland-Redland Bay Road near Boundary Street upgrade project map

Cleveland Redland Bay Road near Boundary Street upgrade project map outlining work to be undertaken

Cleveland-Redland Bay Road and Serpentine Creek Road upgrade project map

Cleveland Redland Bay Road and Serpentine Creek Road upgrade