Skip links and keyboard navigation

Carnarvon Highway Upgrade Program

Overview:

The Carnarvon Highway Upgrade Program (CHUP) will see widening works take place on various sections of the highway between St George and Surat and Injune and Rolleston.

Location:

Carnarvon Highway (St George - Surat)

Carnarvon Highway (Injune - Rolleston)

Regions:
Downs South West Region - South West District

Project info

CHUP will provide targeted road widening upgrades to various sections of the Carnarvon Highway between St George and Surat and Injune and Rolleston.

Project sites

These tables will be updated as works are due to start and finish.

Current works

Carnarvon Highway (St George - Surat)

Site Start Finish
1.61 to 8.86km 27 June 2019 Expected 20 December 2019

View the project map

Carnarvon Highway (Injune - Rolleston)

Site Start Finish
Site 1A – 56.65 to 58.267km to be confirmed
Site 1B – 58.37 to 60.1km to be confirmed  

View the project map

Completed works

Carnarvon Highway (St George - Surat)

Site Start Finish
Site 1 - Phase 1:

 

  • 17.6 to 18.9km
  • 19.2 to 20.1km
 13 March 2017 22 April 2017
Site 1 - Phase 2: 20.1 km - 25.7 km 8 May 2017 30 June 2017
Site 2: 25.7 km to 47.9 km 5 February 2018  9 May 2018 
Site 3: 48.3 km to 66.7 km 10 September 2018  2 November 2018 
Site 4: 74.2 km to 82.0 km 10 September 2018  6 December 2018  
Site 5: 95.8 km to 101.0 km 10 September 2018  6 December 2018  

View the project map

Carnarvon Highway (Injune - Rolleston)

Site Start Finish
Site 1: 38.2 km to 46.1 km 10 October 2017  21 April 2018 
Site 2: 52.9 km to 54.5 km 6 March 2017 12 April 2017
Site 3: 61.7 km to 68.1 km 26 February 2018  16 October 2018 