Gregory Developmental Road: Charters Towers to the Lynd

Overview:

Pavement widening and strengthening approximately 16 kilometres of narrow sections on the Gregory Developmental Road.

Location:

Gregory Developmental Road, between Charters Towers and the Lynd.

Completion:

Construction commenced on the first site in June 2017; and construction at all sites is expected to be complete in early 2020.

Benefits:

This upgrade will improve safety and efficiency for road users.

Supplier:

Both Charters Towers Regional Council and RoadTek are delivering the project on behalf of the Department of Transport and Main Roads.

Funding:

The $42.28 million project is funded by the Queensland Government.

Regions:
North Queensland Region

Project info

Both Charters Towers Regional Council and RoadTek will be delivering the pavement widening and strengthening works at a number of work sites between 2016-17 and 2019-20.

Construction of the first section between Bluff Downs Road and Basalt River Bridge was completed in June 2018.

Construction of the second section extending north-west from Basalt River Bridge commenced in August 2018. Work is being carried out by Charters Towers Regional Council and is due to be complete in mid-2019.

Construction of the third section will be carried out by RoadTek, with construction planned to commence early-mid 2019.

Works at all sites are expected to be completed in early 2020, weather permitting.

The pavement widening and strengthening works will improve safety for all users of Gregory Developmental Road, particularly heavy vehicles.

Community info

The project's Customer & Stakeholder Management team is committed to listening to stakeholders and values all community feedback during the project's construction.