Springfield Central train station, Sir Llew Edwards Drive, construct park 'n' ride

Construction is complete on the multi-storey park 'n' ride that services the Springfield Central train station.

More parking spaces have been created for the Springfield Central train station, as well as improved safety and security for people in and around the station precinct. The carpark features, elevators, additional accessible parking spaces close to the station and greater security through CCTV and lighting.

Benefits

  • Improves safety
  • Increases car parks
  • Reduces peak hour congestion
  • Contributes to economy

Key features

  • Multi-storey park 'n' ride carpark facility bringing the total number of carparks around the Springfield Central train station precinct to around 1,100.
  • Elevators, additional accessible parking spaces close to the station and greater security through CCTV and lighting.

Funding

This project was fully funded by the Queensland Government.

Total investment
$44.5 million
Queensland Government
$44.5 million

Current status

The new multi-storey carpark was opened on Saturday 30 April 2022.

Springfield Central train station park 'n' ride timelapse

Video description

This video shows time lapse footage of construction for the Springfield Central station park 'n' ride.

Project timeline

30 April 2022
The new Springfield Central station park 'n' ride carpark opened to the public.
February 2022
The new Springfield park 'n' ride carpark can be seen by all commuters and customers, as scaffolding is removed unveiling the modern façade.
December 2021
The main concrete works on all 4 levels are completed. Concrete works on the double helix ramp at the middle of the carpark is also complete. The façade and lift installation is in progress.
February 2021
The installation of the tower crane signals a shift in project phases, moving from ground works to construction of the new multi-storey facility.
September 2020
The construction tender was awarded to ADCO Construction Pty Ltd in late September 2020.
The start of construction commenced late September 2020.

For more information on the timing and what the works include, read the stakeholder notification.
May 2020
The construction tender was released in May 2020.

Springfield Central train station, Sir Llew Edwards Drive, construct park 'n' ride precinct map

Aerial map showing the placement and connectivity of the new park 'n' ride facility and the Springfield Central Train Station.