Barcaldine-Aramac Road widening project

We delivered upgrades to the Barcaldine-Aramac Road.

Project activities included widening and sealing more than 6.5km of the road between Barcaldine and Aramac.

Benefits

  • Improves safety
  • Increases capacity
  • Improves network efficiency
  • Better road access
  • Contributes to regional growth

Key features

  • Widened and sealed 6.5km of the road.
  • Provided additional overtaking opportunities. 

Funding

The project was funded by the Queensland Government.

Total investment
$2.09 million
Queensland Government
$2.09 million

Current status

Works started in February 2019 and were completed in May 2020. Barcaldine Regional Council were the construction contractors.

For more information view the Media statement - Monday, February 18, 2019 Road widening to begin on Barcaldine-Aramac Road.

Barcaldine–Aramac Road widening project map