Cramsie - Muttaburra Road, (Section 4) pave and seal

The last remaining gravel section of Cramsie - Muttaburra Road is set to be sealed.

Works will soon start to seal the final 4km section of gravel road, improving safety, efficiency and wet weather access for all road users travelling between Longreach and Muttaburra. 

The road is part of a key link that connects central Queensland with northern and southern parts of Australia. It gives surrounding communities access to goods and services, education, employment and recreation facilities. 

Construction is expected to start in early 2022 and when completed in mid-2022, the road will be fully sealed. 

Fully sealing the Cramsie - Muttaburra Road complements existing sealed access to Muttaburra via Barcaldine and Aramac, creating a sealed loop to support growth in tourism opportunities. 

Benefits

  • Improves safety
  • Increases capacity
  • Improves network efficiency
  • Improves flood immunity
  • Reduces travel time
  • Contributes to economy
  • Contributes to regional growth
  • Reduces maintenance

Key features

  • Seal the last 4km gravel section of the road to a width of 6m.
  • Improves safety.
  • Improves travel times and wet weather access.
  • Provides additional overtaking opportunities.

Funding

This project is fully funded by the Queensland Government. Investment ID 1078784

Total investment
$2.2 million
Queensland Government
$2.2 million

Current status

The project is in the pre-construction phase. Construction is expected to start in early 2022 with completion in mid-2022. 