Location
The preserved rail corridor spans across 8.3 kilometres and link the North Coast Line at Abbott Street to the Port of Townsville.
Status
Planning

Townsville Eastern Access Rail corridor

The Townsville Eastern Access Rail Corridor (TEARC), is a proposed rail freight connection between the North Coast Rail Line and the Port of Townsville.

The Port of Townsville is a key transport hub supporting regional and state economic activity. The preservation of the TEARC corridor supports long-term planning for freight efficiency and network connectivity across northern Queensland, including potential connections to the Mount Isa rail system.

The corridor is being preserved to ensure land remains available for a future rail link should freight demand increase over time. If developed, the project has the potential to improve traffic flow, enhance safety, and reduce the number of freight trains passing through the Townsville city centre.

The TEARC is a long-term infrastructure initiative supporting the Port of Townsville’s ongoing role as a key economic driver for Queensland.

Image of Townsville Eastern Access Rail Corridor

Benefits

  • Increases capacity
  • Improves network efficiency
  • Improves flood immunity
  • Contributes to economy
  • Contributes to regional growth
  • Reduces maintenance

Funding

The project is jointly funded by the Australian and Queensland governments. Investment ID: 738293 QTRIP 2024-25 to 2027-28

Total investment
$12.5 million
Australian Government
$6.25 million
Queensland Government
$6.25 million

Current status

Project background

In November 2017 - Building Queensland completed a detailed business case, assessing the viability of the project. The assessment found that, at that time, the costs of constructing the rail line outweighed the benefits.

These findings were accepted by both the Queensland Government and the Australian Government in early 2018.

Despite this, the corridor is being preserved to ensure land is available should future demand support development. Preservation activities include planning protections, environmental considerations and, where required, land acquisition.

Stakeholder engagement

Stakeholder consultation is underway and will continue as planning progresses.

Last updated: 2 July 2026