Key aspects of the TIC-DC

  • replaces the current Design and Construct Contract
  • can be used for the construction of all forms of transport infrastructure (such as roads, marine structures and busways)
  • for open tendering (one-stage or two-stage process), and  
  • contains dispute resolution alternatives, such as 'Issues Resolution Advisor' and 'Dispute Resolution Board'
Any new tenders from September 2015 will be required to use the TIC-DC templates.
 
The department is using TIC-DC for all design and construction contracts from September 2015, unless an Early Contractor Involvement contract is appropriate. Please contact Director (Infrastructure Procurement/Infrastructure Delivery Services) with any inquiries on design and construct-style projects.
 
Part 1 - Information for Tenderers  
 
Part 2 - Conditions of Tendering 
 
Part 3 - Tender Forms and Tender Schedules  

 

Part 4 - General Conditions of Contract

 
Part 5 - Additional Contract Requirements  
  • Scope of Works and Technical Criteria (SWTC) - Please contact the department's Infrastructure Procurement Unit, Infrastructure Delivery Services to develop this document.
  • C7836.TIC Clause Bank
 
Part 6 - Standard Documents 
 
Part 7 - Project Specific Documents 
 
Part 8 - Other Documents  
 
Administrative Forms (not included in Tender Documents)
 
Dispute Resolution