Overview:

The Everton Park Link Road will connect South Pine Road, north of the Kedron Brook Creek, to Stafford Road, east of Mountridge Street.

Location:

Everton Park.

Benefits:

On completion of the Everton Park Link Road, the project benefits will include:

  • a direct route between Stafford Road and South Pine Road, reducing traffic congestion at the Stafford Road and South Pine Road intersection
  • removal of the right turn facility from South Pine Road into Stafford Road during peak hours, providing more traffic light ‘green time,’ and improving travel time at the intersection
  • increased connectivity for cyclists with dedicated facilities including a link to the Kedron Brook Bikeway
  • increased pedestrian accessibility around shopping precincts with wider footpaths and additional crossings at the Everton Park Link Road intersection.
Funding:

$26 million (Queensland Government).

Regions:
Metropolitan Region

Project info

The Everton Park Link Road is stage one of a two stage plan to improve traffic flow and safety at the intersection of Stafford and South Pine Road. The link road will connect to South Pine Road, north of the Kedron Brook Creek, and Stafford Road, east of Mountridge Street.

Design is currently underway and is expected to be finalised by mid-2019, with construction tender award expected in late 2019. 

The majority of the Everton Park Link Road will be constructed away from operating roads, and traffic impacts will be minimised during construction. 

There will be some unavoidable removal of trees, and the project will include landscaping to improve the amenity.

Fact sheet

Project map

Contact details

Email: metropolitanregion@tmr.qld.gov.au
Phone: 07 3066 4338
Post: Department of Transport and Main Roads
Metropolitan Region
PO Box 70
Spring Hill Qld 4004
Last updated
26 July 2019