A new multi-storey park ‘n’ ride is being built to service Springfield Central station.

The Springfield Central station park 'n' ride will create more parking spaces for the Springfield Central station. It will also improve safety and security for people in and around the station precinct, featuring 24-hour access, elevators, additional accessible parking spaces close to the station and greater security through CCTV and lighting.

The Queensland Government has committed $44.5 million to deliver the multi-storey park 'n' ride at Springfield Central station, with around 1,100 park 'n' ride spaces across the precinct once completed.

Benefits

  • Improves safety
  • Increases car parks
  • Reduces peak hour congestion
  • Contributes to economy

Key features

  • Multi-storey park ‘n’ ride carpark facility that will bring the total number of available carparks around the Springfield Central station precinct to approximately 1,100.
  • 24-hour access, elevators, additional accessible parking spaces close to the station and greater security through CCTV and lighting.

Funding

Total investment
$44.5 million
Queensland Government
$44.5 million

Current status

We are currently undertaking construction of the multi-storey carpark. 

February 2021
The installation of the tower crane signals a shift in project phases, moving from ground works to construction of the new multi-storey facility.  
September 2020

The construction tender was awarded to ADCO Construction Pty Ltd in late September 2020.

The start of construction commenced late September 2020. For more information on the timing and what the works include, read the stakeholder notification

The project aims to be completed early 2022.

May 2020

The construction tender was released in May 2020.