• North Queensland Region
  • Bruce Highway Upgrade Program
Location
Bruce Highway, 6km north of Ingham
Timing
Detailed design was completed in December 2025
Status
Procurement

Bruce Highway (Ingham – Innisfail), Gairloch Floodway, improve safety

The Queensland Government is delivering an upgrade of the Bruce Highway at Gairloch Floodway to enhance safety and flood resilience along this complex and flood-prone section of the highway. Key improvements include road realignment, wide centre line treatment, and removal of a sharp curve to improve traffic flow and reduce flood-related disruptions.

Located within a 16km section of the Bruce Highway, from Ingham's southern outskirts to the Cardwell Range foothills, this area experiences regular flooding and road closures. Currently, the annual average time of submergence of this location is 1.4 days, which is expected to be reduced by more than half. The flood likelihood will drop from 54% to approximately 33% per year with the new alignment.

Benefits

  • Improves safety
  • Improves network efficiency

Key features

  • Realignment of approximately 1.6km of the Bruce Highway to remove a sharp curve and straighten the road
  • Implementation of wide centre line treatment to increase separation between vehicles and reduce the risk of head-on crashes
  • A new bridge on the Bruce Highway at the Gairloch Floodway
  • New culvert infrastructure
  • Improved property access connections

Funding

This project is funded by the Australian Government. 

The project scope, cost and timing are subject to further planning, consideration and negotiation with the Australian Government.

Investment ID: 2129809

Total investment
$48 million
Australian Government
$48 million

Current status

Detailed design was completed in December 2025. In early December 2025, we released the construction tender for the Bruce Highway (Ingham–Innisfail) program of works between Ingham and Cardwell Range, which includes the Bruce Highway (Ingham–Innisfail), Gairloch Floodway, improve safety project.

Project timeline

Milestone Date
Project planning commenced November 2021
Planning phase completed 2023
Tender for detailed design award August 2024
Detailed design commenced September 2024
Detailed design completed December 2025
Construction expected to commence Mid-2027 (weather permitting)

Project location map

Map showing the location of a 1.6km upgrade section north of Ingham. The planned works will straighten the highway by removing an existing curve at the Gairloch Floodway, enhancing both safety and flood resilience.

Map showing the location of work to be completed on Bruce Highway (Ingham - Innisfail), Gairloch Floodway, safety improvements project
Map of upgrades to a 1.6km section of the Bruce Highway (north of Ingham) at the Gairloch floodway to remove a curve in the road and straighten the highway.

Last updated: 17 February 2026