Captain Cook Highway Cairns – Mossman 2024 Disaster Recovery Funding Arrangements reconstruction
The Queensland Government has made significant progress on the reconstruction works along the Captain Cook Highway. As part of the comprehensive disaster recovery program, these works aim to restore vital infrastructure and prioritise the safety of all road users.
More than 250 sites along the highway were damaged because of Ex-Tropical Cyclone Jasper. There were 85 geotechnical sites to be repaired, with works now completed on 42 of these sites. There are a further 95 civil sites and 70 pavement sites being repaired along the highway, with works now completed on more than 45 sites.
Key stabilisation measures include:
- Protecting slopes to prevent erosion and landslides.
- Installing soil anchoring systems for stability.
- Adding debris flow barriers to protect against falling rocks and ensure safer travel.
Additional civil works involve resurfacing damaged roads, repairing culverts, restoring drainage systems, and replacing and fixing road signs and barriers.
These efforts will restore the highway to its pre-cyclone function, ensuring it remains safe and operational for the community and businesses.
Benefits
- Contributes to regional growth
- Contributes to economy
- Restores damaged infrastructure
Key features
- Restoring access for communities and businesses.
- Restoring damaged roads and road surfaces.
- Repairing damaged slopes and batters along roads.
Current status
- Start date: Early 2025
- Expected completion: Most reconstruction works are expected to be completed by early 2027, site and weather conditions permitting. Some works may take longer due to the severity of the damage.
- Current progress: Works are underway.
Captain Cook Highway northern sites map

Captain Cook Highway southern sites map

Debris flow barriers
The installation of debris flow barriers along the highway is a significant milestone in Far North Queensland’s recovery efforts.
A first for Far North Queensland’s state-controlled roads, the barriers are designed to catch the solid debris while allowing for the flow of water into culverts and drains along the highway.
This reduces the potential for long-term road closures at these sites during and after extreme weather.
Of the 7 debris flow barriers to be installed, 2 were completed by late 2025, and 1 was completed in May 2026. The remaining 4 are expected to be completed by the end of 2026, site and weather conditions permitting.
