Mossman – Daintree Road, 2024 Disaster Recovery Funding Arrangements reconstruction works
Reconstruction works are underway on a section of Mossman – Daintree Road damaged during ex-Tropical Cyclone Jasper.
Disaster recovery is a long-term process and involves an extensive program of works and complex solutions.
A variety of stabilising techniques are being used, including:
- reinforcing the slopes
- soil anchoring systems
- vertical retention piling
- building rock retaining walls.
These repairs will ensure the road is returned to its fully operational pre-cyclone function.
Benefits
- Contributes to regional growth
- Contributes to economy
- Restores damaged infrastructure
Key features
- Restoring access for communities and businesses.
- Restoring damaged roads and road surfaces.
- Repairing damaged slopes and batters along roads.
Project overview
Reconstruction works involves stabilisation works below the road.
More than 1,500 linear metres of soil nails and more than 30 concrete piles drilled vertically to depths of more than 15m into the ground to stabilise the downslope hillside.
A combined 30m retaining wall, and a 50m rock gabion wall will also be installed to support the hillside.
Mossman Daintree Road cyclone reconstruction works
Funding
The recovery works are jointly funded by the Australian and Queensland Governments through the Disaster Recovery Funding Arrangements (DRFA).
Current status
Significant progress has been made restoring the Mossman – Daintree Road to its pre-event function following Tropical Cyclone Jasper in December 2023.
Humbug Reach
Reconstruction works at the Humbug Reach are progressing well and remain on track for completion by the end of 2026. Stabilisation works, including piling, a concrete retaining wall, and gabion retaining wall (galvanised steel mesh baskets) have been completed, and the roadway restored.
The remaining works include asphalt surfacing, kerb and channel installation, guardrail installation, and line marking. Upon completion of these activities, the road will be reopened to two-way traffic.
Project map
Mossman – Daintree Road
Resurfacing works on multiple sections of the Mossman–Daintree Road are progressing well and remain on track for completion by the end of 2026. These improvements will help strengthen the pavement, make the road more resilient to future severe weather, and reduce the need for ongoing maintenance. Pavement works are now underway to restore the full width of the road and enable two-way traffic once completed.