Warrego Highway Upgrade Program

The 796km Warrego Highway is Queensland's principal east-west route, connecting people and freight from Charleville to Ipswich. The improvements being delivered under the Warrego Highway Upgrade Program (WHUP) are essential to the region's economic growth and will benefit the agriculture, resources and tourism industries.

The WHUP comprises 20 projects being delivered between Toowoomba and west of Miles. The $635 million investment is jointly funded by the Australian and Queensland governments, with the Australian Government contributing $508 million and the Queensland Government contributing $127 million.

The Warrego Highway upgrades will contribute to the nation's productivity by increasing efficiency, safety and reliability of the National Land Transport Network.

Current projects

Chinchilla open level rail crossing upgrade

  • a $19 million project to improve safety at the open level rail crossing in Chinchilla. Construction began in May 2019. Package 4 (Colamba Street signals project) of the Oakey to Miles Safety Upgrade is being delivered with the open level crossing project.

Oakey – Miles safety upgrade

  • a $43.5 million project of road treatments to improve safety on the busiest sections of the highway. Package 1 was completed November 2017. Packages 2, 3 and 5 were completed in January 2019. Package 4 is being delivered with the Chinchilla open level rail crossing upgrade.

Dalby to Miles pavement widening and safety upgrade

  • a $63.64 million project to upgrade the highway and improve safety with pavement widening and wide centre line treatments that separate opposing lanes of traffic. Construction commenced in February 2019. This project is funded through savings realised from completed WHUP projects.

Oakey to Miles safety upgrade stage 2

  • a $11.65 million project to upgrade the highway and improve safety with additional stopping bays, and the removal of dangerous drop-offs at the road’s edge and roadside hazards. Construction started in February 2019. This project is funded through savings realised from completed WHUP projects.

Warrego Highway East and West Creek Culvert Upgrades

  • a joint $16.9 million project to improve flood immunity in the Toowoomba central business district through the upgrade of culverts at 2 locations. This project is funded through savings realised from completed WHUP projects. Construction activity started in mid-2019. 

Completed projects

Dalby – Miles overtaking lanes

  • a $35 million project to provide additional overtaking lanes at regular intervals in both directions. Construction started January 2018 and was completed in March 2019.

Carroll Creek culvert replacement

  • a $4.9 million project to replace the culverts at the site west of Yuleba to improve productivity for road freight operators. Construction began in November 2018 and was completed in May 2019. This project was funded through savings realised from completed WHUP projects.

Brigalow – Chinchilla upgrade

  • a $33.5 million project to widen 11km of the highway on the eastern approach to Chinchilla. Completed May 2017.

Dalby eastern access upgrade

  • a $56 million project to upgrade the highway and improve motorist and pedestrian safety at major intersections through the eastern half of Dalby. Construction started August 2017 and was completed in November 2018.

Dalby western access upgrade

  • a $59 million project to upgrade the highway and improve safety at major intersections and accesses from nearby industrial development on the western side of Dalby. Construction started August 2017 and was completed in November 2018.

Drillham – Palardo upgrade

  • a $13 million project to widen narrow sections of the highway to a safe standard for heavy vehicles. Construction started in May 2018 and was completed in March 2019.

Jingi Jingi Creek bridge upgrade

  • a $10.6 million project to replace the deteriorated culverts and build a new concrete bridge at Jingi Jingi Creek. Completed August 2017.

Jondaryan - Sabine Road intersection upgrade

  • a $3.9 million project to improve the intersection at Sabine Road, Jondaryan so heavy vehicles have safe access to the highway. Completed January 2017.

Miles western access upgrade

  • a $11.9 million project to widen and rehabilitate the highway through the town and on the western outskirts. Construction started in May 2018 and was completed in October 2018.

Oakey – Dalby overtaking lanes

  • a $36.8 million project to provide additional overtaking lanes at regular intervals in both directions. Completed September 2017.

Toowoomba – Oakey duplication stage 1

  • a $62.7 million project to extend the 4-lane Warrego Highway from Nugent Pinch Road to west of Charlton. Completed in July 2016.

Toowoomba – Oakey duplication stage 2

  • a $71.1 million project extending the 4-lane highway from the stage 1 project a further 4km westward to Kingsthorpe. Construction was completed in March 2018.

Planning projects

Chinchilla heavy vehicle route strategy

  • a $1 million project to investigate the need for a future heavy vehicle route for Chinchilla due to growth in highway traffic, population and commerce.

Toowoomba – Oakey duplication stage 3 planning project

  • a $2 million planning project to investigate the proposed 4-lane highway construction from Kingsthorpe to Oakey was completed in July 2018.

Community information

Disruption to travel due to road works on the Warrego Highway west of Toowoomba should be factored in to your travel plans. Please be patient and observe all road signage and traffic management instructions.

Last updated
31 July 2019