Coomera Connector (Stage 1), Coomera to Nerang
The Stage 1 section of the Coomera Connector between Coomera and Nerang is around 16km and has been identified as the priority section to be built first.
Delivery approach
The Coomera Connector (Stage 1) will be delivered in 3 construction packages:
- Stage 1 North Shipper Drive, Coomera to Helensvale Road, Helensvale
- Stage 1 Central Helensvale Road, Helensvale to Smith Street Motorway, Molendinar
- Stage 1 South Smith Street Motorway, Molendinar to Nerang-Broadbeach Road, Nerang.
By constructing additional crossings of the Coomera and Nerang rivers, Stage 1 of the Coomera Connector will reduce pressure on the M1 by providing an alternative route for the growing communities and commercial hubs of Helensvale and Coomera.
Following community consultation in 2020, the northern end point for the Coomera Connector (Stage 1) was confirmed as Shipper Drive, Coomera.
The corridor is wide enough for an ultimate 6-lane motorway and while the Stage 1 route will generally be built to 4 lanes to meet medium-term traffic needs, the Central package will be built to 6 lanes. Key major structures will be future-proofed to 6 lanes, to help minimise future construction impacts to adjacent residents and the travelling public.
Benefits
- Improves safety
- Increases capacity
- Improves network efficiency
- Increases traffic flow
- Reduces peak hour congestion
- Reduces interchange queuing
- Reduces travel time
- Contributes to economy
- Better active transport
Funding
This project is jointly funded by the Australian and Queensland governments. Investment ID 1776678
- Total investment
- $3.026 billion
- Australian Government
- $1.513 billion
- Queensland Government
- $1.513 billion
Current status
Construction of Stage 1 North and Stage 1 Central is now underway.
Early works for Stage 1 South are now underway.
Key milestones
- September 2021: Stage 1 reference project and business case approved by the Queensland Government.
- November 2021:
- Stage 1 North early works agreement awarded to complete the detailed design of this section
- Stage 1 Central design and construct proposal released to industry for tenders.
- 18 February 2022: Stage 1 reference project and business case approved by Infrastructure Australia.
- Early 2022: Stage 1 Central competitive and confidential tender process underway.
- August 2022: Design contract awarded for Stage 1 South.
- Late 2022:
- Public Environment Report released for public comment
- Stage 1 South preliminary and detailed design started.
- Early 2023:
- Environmental approvals granted
- Stage 1 North main road construction started
- Stage 1 Central early works contract awarded.
- Late 2023 Stage 1 Central site preparation works commence. Stage 1 South design released to the community.
- Early 2024: Stage 1 Central enabling works commenced and design released to the community.
- Mid 2024: Stage 1 South early works commenced.
- Late 2024: Stage 1 Central main construction works contract awarded.
- Early to mid-2025: Stage 1 South main road construction to start.
- Late 2025: Stage 1 is expected to progressively open to traffic in sections.
Coomera Connector (Stage 1) project map

Coomera Connector (Stage 1) animations
A series of animated concepts for Stage 1 was developed to demonstrate what the Coomera Connector may look like when constructed in the ultimate 6-lane configuration. As the project has progressed through the reference design phase and consultation, some features have changed. View the initial 360 degree panoramas of Coomera Connector Stage 1.
Business case summary for Stage 1
The business case for the Coomera Connector (Stage 1) was approved in September 2021 by the Queensland Government and in February 2022 by Infrastructure Australia with additional funding secured to cover increased costs resulting from a competitive building and construction market due to COVID-19, and higher material and labour costs being experienced throughout Australia.
The complete Stage 1 business case is more than 1,000 pages and details the extensive investigations and data completed by numerous content-experts specific to their relevant fields. On that basis, the majority of the report is commercial-in-confidence.
Read the Stage 1 business case summary.
Download the Stage 1 business case summary (PDF, 9.62MB).
View the Infrastructure Australia summary evaluation of the business case.
Community consultation
The department performed initial community consultation on the 45-km Coomera Connector corridor in late 2019. Outcomes from this indicated that 80% of participants supported the Coomera Connector being built as soon as possible. It also showed that noise, landscape, and environment were key issues raised by those who live close to the Coomera Connector.
The department held a second round of community consultation focusing on Stage 1 in September 2020. This consultation gave the community an added opportunity to have their say on key priorities for the project.
In addition to this, a Coomera Connector (Stage 1) Community Reference Group was established for the business case phase of the project. The purpose of the Community Reference Group was to gain community input from key resident, business and environmental stakeholders into negotiable aspects of the project.
As the business case is now finalised, the purpose, scope and objectives of the Community Reference Group is complete. Its input has been valuable in understanding community priorities and has been instrumental in guiding key urban design and environmental elements of the project.
The urban design elements explored by the Community Reference Group and identified as community priorities were:
- design of noise barriers
- design of retaining walls
- landscaping and planting in and around the project corridor
- design of a shared path for walking and bike riding.
A series of artist's impressions were developed, based on the ultimate 6-lane design, to show how these elements could look for the Coomera Connector (Stage 1).
The department requested feedback from the wider community on the artist's impressions in March 2021, and this feedback was considered as part of the design process.
Download the Questions, Issues and Opportunities report from the Community Reference Group.
View other historical publications for the Coomera Connector.
Environmentally sensitive design
To ensure the Coomera Connector is designed and delivered in an environmentally sensitive manner, the department has been working with a range of subject matter experts and stakeholders.
Over the past 4 years, extensive surveys have been conducted along the Stage 1 corridor, including:
- wildlife surveys to determine habitat values for native fauna, including koalas
- flora surveys to determine the presence of protected plants
- aquatic ecological surveys and water quality monitoring, including a 12-month survey within and adjacent to Coombabah Lake.
Environmental approvals have progressed, with the Australian Department of Climate Change, Energy, the Environment and Water (DCCEEW) assessing Stage 1 of the project under the Environment Protection and Biodiversity Conservation Act 1999. DCCEEW confirmed the Coomera Connector (Stage 1) to be a controlled action that was assessed by a Public Environment Report.
The draft Public Environment Report was released for public review and comment from 11 October 2022 to 15 November 2022.
DCCEEW granted approval for Stage 1 of the project in March 2023 and approved the offset area management plan in August 2024.
Koala management plan
Recognising the significance of koala populations in the northern Gold Coast, the department has developed a Koala Management Plan as part of our responsibilities to deliver Stage 1 of the Coomera Connector.
The Koala Management Plan will guide the design and implementation of a suite of measures to understand the current extent and health of the koala population in the vicinity of the Coomera Connector project area and ensures that koalas are appropriately protected during construction and operation. This approach ensures that the department complies with relevant state and federal legal requirements and meet community expectations for the welfare and conservation of koalas in and around the corridor.
Conservation strategies forming the basis of the Koala Management Plan include:
- undertaking monitoring and research to provide baseline data on koala populations
- best practice fauna movement infrastructure to facilitate the movement of koalas in wildlife corridors
- working with all levels of government to establish potential future koala habitat areas (local offsets) and maintain important wildlife corridors.
In August 2021 the department engaged Endeavour Veterinary Ecology to undertake a koala tagging and monitoring program, and a Koala Stakeholder Reference Group and established a koala management program to share information on the progress of the program.
To ensure that impacts to habitat are addressed, the plan also includes the acquisition and rehabilitation of additional land to support local wildlife populations and to offset areas of habitat lost for the Coomera Connector.
The Koala Management Plan is included in the Public Environment Report.
As part of an extensive research program, the Coomera Connector (Stage 1) project has also provided funding to EVE in their research, development and trials of a new and innovative koala 'doggy door'. Officially called the 'Fauna Escape Hatch', this device will allow one-way movement of animals through the structure. Testing in near-real-world conditions is now underway and results so far are compelling with koalas opting to use the hatch 100 per cent of the time when it is available.